Transformer Upgrade

Upgrading power transformer from 1x20 MVA to 3x20 MVA
Contractor: Doosan Heavy Equipment LLC


Installation of 11 KVPanels, Transformers , RMU & LV Panels

Erection, testing & commissioning of substations, panels and transformer
Contractor: Al Raffa Trading & Contracting LLC


Samail PSS

Testing & commissioning of 3x20 MVA tranformer, 33KV & 11KV panel equipment and protection relay testing
Contractor: Sharikah Fanniyah Omaniyah (Muscat) LLC

al Batha PSS

Testing & commissioning of 3x20 MVA tranformer, 33KV & 11KV panel equipment and protection relay testing
Contractor: Eastern Overseas Trading & Contracting LLC

Adam PSS

Installation of 33KV & 11KV panels (2x20 MVA), capacitor bank, power transformer, station transformer, CR panels, battery bank & SCADA panels.
Contractor: Sharikah Fanniyah Omaniyah (Muscat) LLC

Mullandha PSS

Installation of 33KV & 11KV panels (2x20 MVA), capacitor bank, power transformer, station transformer, CR panels, battery bank & SCADA panels.
Contractor: Sharikah Fanniyah Omaniyah (Muscat) LLC

Mullandha Industrial Area PSS

Installation of 33KV & 11KV panels (2x20 MVA), capacitor bank, power transformer, station transformer, CR panels, battery bank & SCADA panels.
Contractor: Sharikah Fanniyah Omaniyah (Muscat) LLC


Autorecloser

Testing & commissioning of 11 KV OHL autorecloser
Contractor: Sharp Overseas Trading & Contracting LLC

Transformer Upgrade

Upgrading of power transformer from 10 MVA to 20 MVA. Removal of 10 MVA transformer and power cables. installation of 20 MVA tranformer and oil filteration
Contractor: Sharikah Fanniyah Omaniyah (Muscat) LLC

Al Hail PSS

3x20 MVA transformer Installation in 33/11KV. Testing & commissioning of 20 MVA tranformer, 33 KV & 11 KV panel equipment and protection relay testing
Contractor: Rukun Al Yaqeen (RAY) International LLC

Tarif PSS

3x20 MVA transformer Installation in 33/11KV. Testing & commissioning of 20 MVA tranformer, 33 KV & 11 KV panel equipment and protection relay testing
Contractor: Sharikah Fanniyah Omaniyah (Muscat) LLC


ADAM Airbase

Testing & commissioning of 2 MVA tranformer, 11 KV panel equipment and protection relay testing, Cable High Voltge Test, RMU & LV panels.
Contractor: Larsen & Toubro (Oman) LLC.

Duqm Jaaluni Airport, Al Wusta

Testing & commissioning of 5 MVA tranformer, 11 KV panel equipment and protection relay testing, Cable High Voltge Test, RMU & LV panels.
Contractor: Al Rafaa Trading & Contracting LLC (ARTCO)

Khasab Airport

Testing & commissioning of 5 MVA tranformer, 11 KV panel equipment and protection relay testing, Cable High Voltge Test, RMU & LV panels.
Contractor: Power Advantage International LLC


Al Khoudh PSS

3x20 MVA transformer Installation in 33/11KV. Testing & commissioning of 20 MVA tranformer, 33 KV & 11 KV panel equipment and protection relay testing
Contractor: Rukun Al Yaqeen (RAY) International LLC

Airport Heights PSS

3x20 MVA transformer Installation in 33/11KV. Installation of 33 KV & 11 KV Panels, Capacitor Bank, Power Transformer, Station Transformer, CR Panels, SCADA Panels, laying of power cable & termination.
Contractor: Rukun Al Yaqeen (RAY) International LLC


Salalah International Airport

LV Panels Installation, Testing & Commissioning
Contractor: Al Rafaa Trading & Contracting LLC (ARTCO)


Oman Liquified Natural Gas Plant

Complete maintainence of 11KV, 6.6KV feeders and 10 MVA transformers
Contractor: Oman Liquefied Natural Gas (OLNG) - Project Division


New Oman Container Terminal

33KV & 11KV PSS Installation,Testing & Commissioning
Contractor: Al Rafaa Trading & Contracting LLC (ARTCO)


Khasab Power Plant

6x13.5 MW - Testing & Commissioning
Contractor: Al Jood Trading & Contracting Co. LLC

Dibba HYOSUNG GIS Grid Station

132KV HYOSUNG GIS 1. CT/VT testing 2.CB timing 3.Busbar contact resistance 4.Disconnector,Earth switch contact resistance,timimg 5.Bay/Bus Interlock test
Contractor: Saudi National Contracting Company LLC

Khasab PSS

Testing & Commissioning of 33KV SIEMENS GIS equipment, control panel and ProtectionRelay Testing.
Contractor: Saudi National Contracting Company LLC


Sur Water Desalination Plant

Testing & Commissioning of 5 MVA tranformer, 11KV panel equipment and Protection Relay testing, Cable High Voltge Test.
Contractor: SIDEM Veolia Italy


Partial Shutdown Testing


Annual Maintenance of Protection Relay S/S -A/B - Feeders
Contractor: Technical Trading Co LLC


11 KV Substation Maintenance

Maintenance of underground cables, 11 KV panels, Batteries & Testing


WHO LOVE TO WORK WITH US

We’re as choosy about our clients as they are about us. We choose to partner with clients that understand the importance of being as committed to their customers as they are to their cash. Our clients are bold and willing to take chances. We’re unified in our mission of helping people along their journey—with deep transparency, honesty, and trust. We believe that when people of common passion are brought together, anything is possible—online and offline.